Latest update on eight CPEC infrastructure projects

Date : 09-06-2017

Completing milestones Lahore Orange Line Project:

Brief Introduction: The main line of Lahore orange line project is 25.58km, including underground line 1.07k...   Read more

Latest update on eleven CPEC energy projects

Date : 08-06-2017

1320 MW Sahiwal Power: Completed six months ahead of schedule

Brief Introduction:

Huaneng Shandong Ruyi Sahiwal Project is a large coal-fired prower project jointly invested by Hua...   Read more

Sahiwal Coal-fired Power Plant Energy Project

Date : 07-03-2017

1.    Brief Introduction

Huaneng Shandong Ruyi Sahiwal Project is a large coal-fired power project jointly invested by Huaneng Shandong Power Generation Co.Lt...   Read more

Port Qasim Coal-fired Power Project

Date : 07-03-2017

1. Brief Introduction

Port Qasim Coal-fired Power Project is jointly developed by Powerchina Resources Limited (51% shares) and Al Mirqab Capital (49% shares), which is one ...   Read more